Authors :
Okpan Agara; Onoh Felix Emenike; Adindu Chinedu; Ezichi Ishmel Kalu
Volume/Issue :
Volume 10 - 2025, Issue 8 - August
Google Scholar :
https://tinyurl.com/42nvxhzd
Scribd :
https://tinyurl.com/a97u9znh
DOI :
https://doi.org/10.38124/ijisrt/25aug1205
Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.
Note : Google Scholar may take 30 to 40 days to display the article.
Abstract :
Cost overruns in highway projects constitute a major financial challenge, particularly in Southeast Nigeria,
where they create substantial risks for stakeholders and investors. According to Flyvbjerg et al. (2009), the two principal
causes of cost overruns are optimism bias and strategic misrepresentation. Additional studies have identified a wide range
of contributing factors.To address these challenges, this research develops a conceptual framework aimed at mitigating
cost overruns in highway construction projects. The framework identifies the causes of overruns, explains their effects on
project delivery, and outlines strategies for mitigation (Farooqi & Azhar, 2019). Its purpose is to clarify how cost overruns
originate and provide practical guidance for reducing them.The primary objective is to design and validate a framework
tailored to federal highway projects in Southeast Nigeria. This framework is built using a contextualized, literature-driven
approach that incorporates insights from prior studies on infrastructure cost overruns in Nigeria. The research draws on a
dataset of publicly funded highway projects provided by the Federal Ministry of Works (2006–2016) and employs a
multistage sampling technique. In the first stage, five states in Southeast Nigeria were selected. Data were collected directly
from each state and analyzed to determine the relationship between potential overrun factors and actual cost escalations
using Pearson’s correlation coefficient. Findings reveal that project length, original contract sum, and revised contract
sum are key contributors to cost overruns in the region. Other important factors include material price fluctuations,
design modifications, and project management inefficiencies. The analysis shows a strong positive correlation between
revised contract sums and overall cost overruns. For example, the construction of main works and associated
infrastructure for the Second Niger Bridge (11.79 km, linking Anambra and Delta States) originally contracted at
₦206,151,693,014.87 was revised to ₦300,981,471,801.71, producing a cost deviation of approximately
₦1,094,829,778,786.90.To explain these findings, several theoretical perspectives can be applied, including the Theory of
Constraints, systems thinking, and transaction cost economics. These frameworks emphasize inadequate planning, weak
contract management, and external economic pressures as major drivers of cost escalation.By integrating these insights,
the proposed conceptual framework provides strategies to mitigate cost overruns, reduce financial risk, and improve the
efficiency and success rate of federal highway projects in Southeast Nigeria.
Keywords :
Mitigation, Framework, Project of Overrun, Highway Projects.
References :
- Aibinu, and Odeyinka, (2006). “Construction delays and their causative factors in Nigeria.” J. Constr. Eng. Management, ASCE, (132) 7, pp. 667-677462. Journal of Construction Business and Management, 2, 24-35.
- Akintola, and Eamon, (2000). ‘A survey of current estimating practices in UK’, Journal of Construction Management and Economics, Vol. 18, No. 2, pp.161–172.
- Akoh (2018) Risk Management Framework for Highway Construction Projects in Nigeria.
- Amadi, & Higham ( 2017). latent Geotechnical Pathogens Inducing Cost Overruns In Highway Projects.
- Andersen, Samset & Welde, (2016). Low estimates – high stakes: Underestimation of costs at the front-end of projects. International Journal of Managing Projects in Business, 9(1), 171-193. https:/doi.org/10.1108/IJMPB-01-2015-0008.
- Anigbogu, Ahmad, & Molwus (2019). Cost Overruns on Federal Capital Territory Authority Road Construction Projects. FUTY Journal of the Environment, 13, 1-14.
- Apolot, Ruth ,Alinaitwe, Henry,Tindiwensi, and Dan (2012). “An Investigation into the Causes of Delay and Cost Overrun in Uganda’s Public Sector Construction Projects”, Second International Conference on Advances in Engineering and Technology.
- Arewa (2016). Constructing Africa: Chinese investment, infrastructure deficits, and development.
- Arifin (2018). Calculating the Cronbach's alpha coefficients for measurement scales with "not applicable" option. Universiti Sains Malaysia, 1-8. https://doi.org/10.13140/RG.2.2.16955.87843.
- Asiedu and Alfen (2015) “Understanding the underlying reasons behind time overruns of government building projects in Ghana,” KSCE Journal of Civil Engineering, Vol. 20, No. 6.
- Asiedu and Alfen(2014). “Factors engendering cost misrepresentation of public sector projects in Ghana.” International Journal of Sustainable Construction Engineering and Technology, Vol. 5 No. 2, pp. 13-24.
- Asiedu, and Adaku(2019). Cost overrun in public sector construction projects: A developing c country perspective. International Journal of Managing Projects in Business. https://doi.org/10.1108/IJMPB-09-2018-0177.
- Assiri (2016). Risk of loss of productivity in workplace. International Journal of Scientific and Technological Research, 5(5), 118-120. http://bit.ly/2INpfSQ.
- Author Puteh, & Ong (2017). Quantitative data analysis: Choosing between SPSS, PLS and AMOS in social science research. International Interdisciplinary Journal of Scientific Research, 3(1), 14-25. http://bit.ly/32qeBur.
- Azhar Farooqui and Ahmed, (2010); "Cost Overrun Factors in Construction Industry in Pakistan". Proceeding of First International Conference on Construction in Developing Countries (ICCIDE-1), Karachi, Pakistan, 4-5 August, pp: 499-508.
- Azhar, N., R.U. Farooqui and S.M. Ahmed, (2010); "Cost Overrun Factors in Construction Industry in Pakistan". Proceeding of First International Conference on Construction in Developing Countries (ICCIDE-1), Karachi, Pakistan, 4-5 August, pp: 499-508.
- Buetow ( 2010). Thematic Analysis and Its Reconceptualization as ‘Saliency Analysis’.
- Cantarelli (2011). Cost Overruns in Large-Scale Transport Infrastructure Projects. A Theoretical and Empirical Exploration for the Netherlands and Worldwide. Thesis Series T2010/15, the Netherlands Trail Research School.
- Cantarelli , Flybjerg, Molin & Van Wee (2013). Cost overruns in large-scale transportation. Chileshe & Fianko (2012). An Evaluation of Risk Factors Impacting Construction Projects.
- Cantarelli, C.C., B. Flyvbjerg, B. Wee van, and E.J.E. Molin (2007): "Lock-In and Its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects". Investigating the Way in which Lock-In can Emerge and Affect Cost Overruns. Paper presented at the 88th annual meeting of the Transportation Research Board Washington, D.C.
- Cha and Shin, Compressing Construction Duration (2011): "Lesson Learned for Hong Kong Building Projects" pp. 20-,23-25.
- Chimwaso (2000). ‘An evaluation of cost performance of public projects: Case of Botswana’, Proceedings of the 2nd International Conference of thCIBhttp://buildnet.csir.co.za/cdcproc/docs/2nd/chimwaso_dk.pdf.
- Chin (1998). The Partial Least Squares Approach to Structural Equation Modelling. In G. A.Cornell International Law Journal, 49(1), 101-139. https://scholarship.law.cornell.edu/cilj/vol49/iss1/4/
- Doctor of Philosophy Heriot Watt University, Edinburgh. United Kingdom.
- Doloi, A. (2011): “The rising cost of building construction”. Shelter for Nigerians, NIA Publication, May Edition, pp. 18 – 19.
- Doty and Glick (1994). “Typologies as a unique form of theory building: Toward improved understanding and modelling”, Academy of Management Review, (19) 2, pp. 230- 251effects in Nigeria. Proceedings.
- Everitt, Landau and Leese (2001). Cluster Analysis, Fourth edition, Arnold.
- Fageha, & Aibinu, (2015). Identifying stakeholders ’involvement that enhances project scope definition completeness in Saudi Arabian public building projects. Built Environment Project and Asset Management, 6(1), 6-29. https://doi.org/10.1108/BEPAM-06-2014-0030
- Flyvbjerg (2009). ‘Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it’. Oxford Review of Economic Policy, Volume 25 (3), pp. 344–367.
- FMW&H (2019). List of on-going federal highway projects In: SECTOR, W. (ed.). Federal Ministry of Works and9th July, 2017 in Niamey, Niger Republic. Federal Ministry of Power, Works and Housing Headquaters, Abuja.
- Frimpong, Oluwoye and Crawford, (2003). ‘Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study.’ Int.Ghana. EngDesign Tech., 10-306.Hatamleh, Hiyassat, Ghaleb, & Rateb (2018). Factors affecting the accuracy of cost estimate: Case of Jordan. Engineering, Construction and Architectural Management, 25(1), 113-131. https://doi.org/10.1108/ECAM-10-2016-0232
- Heale & Twycross (2015). Validity and reliability in quantitative research. Evidence-Based Nursing. 18(3), 66-67. https://doi.org/10.1136/eb-2015-102129HealthJournal.Housing,Nigeria:Federal Ministry of Works and Housing, Nigeria infrastructure projects: Explanations and their theoretical embeddedness. arXiv preprint arXiv:1307.2176.International Council for Research and Innovation in Building and Construction. J. Project Management, Vol. 21, pp. 321-326.https://doi.org/10.1080/01446193.2015.1064983Industry. Doctor of Philosophy, Services Research & Policy, 15, 123-125.
- Jennings (2012), “Why costs overrun: risk, optimism and uncertainty in budgeting for the London 2012 Olympic Games”, Construction Management and Economics, Vol. 30 No. 6, pp. 455.
- Kaming, Olomolaiye, Holt, & Harris (1997). ‘Factors Influencing Construction Time and Cost Overruns on High-rise Projects in Indonesia.’ Construction Management and Economics, 15(1), pp. 83-94.
- Lee,and Jin-Kyung (2008), “Cost Overrun and Cause in Korean Social Overhead Capital Projects: Roads, Rails, Airports, and Ports”, Journal of Urban Planning and Development, Vol. 134, No. 2, 5962.
- Leo-Olagbaye & Odeyinka ( 2018). An Evaluation of Risk Factors and their Impact on Road Project.
- Lind, & Brunes (2015). Explaining cost overruns in infrastructure projects: a new framework with applications to Sweden. Construction Management and Economics, 33(7), 554–568.
- Mahamid (2013). Common Risks Affecting Time Overrun in Road Construction Projects in Marcoulides (Ed.), Modern Methods for Business Research.
- Memon, Abdul Rahman, Abdullah & Abdul Aziz (2010). ‘Factors Affecting Construction Cost in Mara Large Construction Project’ perspective of Project Management Consultant.’ International journal of Sustainable Construction Engineering and Technology, 1 (2), pp. 41- 53.
- Muhammad & Sebastian-Dauda (2017). The Public Works Ministries: Organisation, Nigeria: Federal Ministry.
- Odeck, (2004). ‘Cost overruns in road construction what are their sizes and determinants’. of the 6th International Postgraduate Research Conference in the Built and Human Environment, 2006 of Works and Housing.
- Ogbu, & Adindu (2019). Direct risk factors and cost performance of road.
- Ogunlana, & Promkuntong (2016). ‘Construction delays in a fast-growing economy: comparing Thailand with other economies’, International Journal of Project Management, 14(1), pp. 37- 45.
- Olawale, Sun, and Ming (2010), “Cost and Time Control of Construction Projects: Inhibiting Factors and Mitigating Measures in Practice”, Construction Management and Economics, Vol. 20, Issue 5, 509526.
- Omoregie & Radford (2019). Infrastructure delays and cost escalation: Causes and Onolenemen (2013). Road Infrastructure and related development report. Abuja, Operation, Potential Nottingham Trent University. Palestine: Contractor's Perspective. Australasian Journal of Construction Economics and Building, 13(2), 45-53.
- Park, & Papadopoulou (2012). Causes of Cost Overruns in Trasport Infrastructure Projects in Asia: Their Significance and Relationship with Project Size. Bulit Environment Project and Asset Management, 2(2), 195-216.pp. 2103–2111.projects in developing.
- Rahman I A, Memon A H and Karim A T A 2013 Significant factors causing cost overruns in large construction projects in Malaysia, J. Appl. Sci. 13 286–293.
- Ramanathan , Potty and Idrus ( 2012). Analysis of time and cost overrun in Malaysian construction, Adv. Mater. Res. 45 1002–1008.
- Sa'id ( 2019). A Framework for Collaborative Costing in the UK Construction Skamris, & Flyvbjerg (2018). ‘Accuracy of traffic forecasts and cost estimates on large transportation projects’. Transportation Research Record, 1518. Studies and Implementation. Annual Investment Budgets (Last Five (5) Years) Achievement of the Past.Thompson, (2004). Exploratory and confirmatory factor analysis: Understanding concepts and applications. Washington, DC, US: American PsychologicalAssociation.
- Wachs (1990). ‘Ethics and advocacy in forecasting for public policy.’ Business and Professional EthicsJournal 9 (1–2). Zambia. International Journal of Project Management, 27, 522-531.
Cost overruns in highway projects constitute a major financial challenge, particularly in Southeast Nigeria,
where they create substantial risks for stakeholders and investors. According to Flyvbjerg et al. (2009), the two principal
causes of cost overruns are optimism bias and strategic misrepresentation. Additional studies have identified a wide range
of contributing factors.To address these challenges, this research develops a conceptual framework aimed at mitigating
cost overruns in highway construction projects. The framework identifies the causes of overruns, explains their effects on
project delivery, and outlines strategies for mitigation (Farooqi & Azhar, 2019). Its purpose is to clarify how cost overruns
originate and provide practical guidance for reducing them.The primary objective is to design and validate a framework
tailored to federal highway projects in Southeast Nigeria. This framework is built using a contextualized, literature-driven
approach that incorporates insights from prior studies on infrastructure cost overruns in Nigeria. The research draws on a
dataset of publicly funded highway projects provided by the Federal Ministry of Works (2006–2016) and employs a
multistage sampling technique. In the first stage, five states in Southeast Nigeria were selected. Data were collected directly
from each state and analyzed to determine the relationship between potential overrun factors and actual cost escalations
using Pearson’s correlation coefficient. Findings reveal that project length, original contract sum, and revised contract
sum are key contributors to cost overruns in the region. Other important factors include material price fluctuations,
design modifications, and project management inefficiencies. The analysis shows a strong positive correlation between
revised contract sums and overall cost overruns. For example, the construction of main works and associated
infrastructure for the Second Niger Bridge (11.79 km, linking Anambra and Delta States) originally contracted at
₦206,151,693,014.87 was revised to ₦300,981,471,801.71, producing a cost deviation of approximately
₦1,094,829,778,786.90.To explain these findings, several theoretical perspectives can be applied, including the Theory of
Constraints, systems thinking, and transaction cost economics. These frameworks emphasize inadequate planning, weak
contract management, and external economic pressures as major drivers of cost escalation.By integrating these insights,
the proposed conceptual framework provides strategies to mitigate cost overruns, reduce financial risk, and improve the
efficiency and success rate of federal highway projects in Southeast Nigeria.
Keywords :
Mitigation, Framework, Project of Overrun, Highway Projects.