Abstract :
Housing construction projects require effective cost and time control to minimize the risks of delays and cost
overruns. This study aims to analyze cost and schedule performance, identify factors affecting project performance, and
formulate mitigation strategies for two housing construction projects in Maros Regency. The study employs a quantitative
approach using the Earned Value Management (EVM) method to evaluate cost and schedule performance, the Relative
Importance Index (RII) to determine dominant factors, and the Pareto Chart to establish mitigation priorities.
Keywords :
Earned Value Management, Cost and Time Performance, Residential Construction Projects
References :
- Asmaroni, D., & Setiawan, A. (2020). Application of the Earned Value Analysis Method to Cost and Time in Residential Building Construction Projects (Case Study of the Residential Building Construction Project by PT. Graha Praja Kencana in Ceguk Village, Tlanakan Subdistrict, Pamekasan Regency). Ge-STRAM: Journal of Civil Planning and Engineering, 3(1), 31–39. https://doi.org/10.25139/jprs.v3i1.2439.
- Baihaqi, A. H., Afriandini, B., & Suksmono, A. K. (2023). Cost and Time Analysis of a Project Using the Earned Value Method and the Time-Cost Trade-Off Method. Surya Beton: Journal of Civil Engineering, 7(2), 90–101. https://doi.org/10.37729/suryabeton.v7i2.3754
- Biemo, S. W., Abduh, M., & Wirahadikususma Reini, D. P. N. (2006). The Earned Value Concept for Project Management. Journal of Civil and Environmental Engineering, 1–13.
- Furuhitho, X., Setiawan, L., Slameto, J., Ramadhan, R. N., & Susanto, R. H. (2023). Cost and Time Control Planning for the STIE Tazkia Cendikia Bogor Apartment Complex Construction Project Using the Earned Value Method. Journal of Social Science Research, 3, 7591–7600.
- PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK), 6th Edition (PMI, 2017). In Project Management Institute (Vol. 6). http://www.citeulike.org/group/14887/article/9008974.
Housing construction projects require effective cost and time control to minimize the risks of delays and cost
overruns. This study aims to analyze cost and schedule performance, identify factors affecting project performance, and
formulate mitigation strategies for two housing construction projects in Maros Regency. The study employs a quantitative
approach using the Earned Value Management (EVM) method to evaluate cost and schedule performance, the Relative
Importance Index (RII) to determine dominant factors, and the Pareto Chart to establish mitigation priorities.
Keywords :
Earned Value Management, Cost and Time Performance, Residential Construction Projects