Analysis of Cost-Time Performance and Management Strategies for Construction Projects in Maros Regency


Authors : Muhammad Fhauzhan Hazhimah R.; Fahirah F.; Tutang Muhtar Kamaludin; Herminawaty; Ikhsan

Volume/Issue : Volume 11 - 2026, Issue 9 - September


Google Scholar : https://tinyurl.com/3du8ku85

DOI : https://doi.org/10.38124/ijisrt/26sep860

Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.


Abstract : Housing construction projects require effective cost and time control to minimize the risks of delays and cost overruns. This study aims to analyze cost and schedule performance, identify factors affecting project performance, and formulate mitigation strategies for two housing construction projects in Maros Regency. The study employs a quantitative approach using the Earned Value Management (EVM) method to evaluate cost and schedule performance, the Relative Importance Index (RII) to determine dominant factors, and the Pareto Chart to establish mitigation priorities.

Keywords : Earned Value Management, Cost and Time Performance, Residential Construction Projects

References :

  1. Asmaroni, D., & Setiawan, A. (2020). Application of the Earned Value Analysis Method to Cost and Time in Residential Building Construction Projects (Case Study of the Residential Building Construction Project by PT. Graha Praja Kencana in Ceguk Village, Tlanakan Subdistrict, Pamekasan Regency). Ge-STRAM: Journal of Civil Planning and Engineering, 3(1), 31–39. https://doi.org/10.25139/jprs.v3i1.2439.
  2. Baihaqi, A. H., Afriandini, B., & Suksmono, A. K. (2023). Cost and Time Analysis of a Project Using the Earned Value Method and the Time-Cost Trade-Off Method. Surya Beton: Journal of Civil Engineering, 7(2), 90–101. https://doi.org/10.37729/suryabeton.v7i2.3754
  3. Biemo, S. W., Abduh, M., & Wirahadikususma Reini, D. P. N. (2006). The Earned Value Concept for Project Management. Journal of Civil and Environmental Engineering, 1–13.
  4. Furuhitho, X., Setiawan, L., Slameto, J., Ramadhan, R. N., & Susanto, R. H. (2023). Cost and Time Control Planning for the STIE Tazkia Cendikia Bogor Apartment Complex Construction Project Using the Earned Value Method. Journal of Social Science Research, 3, 7591–7600.
  5. PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK), 6th Edition (PMI, 2017). In Project Management Institute (Vol. 6). http://www.citeulike.org/group/14887/article/9008974.

Housing construction projects require effective cost and time control to minimize the risks of delays and cost overruns. This study aims to analyze cost and schedule performance, identify factors affecting project performance, and formulate mitigation strategies for two housing construction projects in Maros Regency. The study employs a quantitative approach using the Earned Value Management (EVM) method to evaluate cost and schedule performance, the Relative Importance Index (RII) to determine dominant factors, and the Pareto Chart to establish mitigation priorities.

Keywords : Earned Value Management, Cost and Time Performance, Residential Construction Projects

Paper Submission Last Date
31 - October - 2026

SUBMIT YOUR PAPER CALL FOR PAPERS
Video Explanation for Published paper

Never miss an update from Papermashup

Get notified about the latest tutorials and downloads.

Subscribe by Email

Get alerts directly into your inbox after each post and stay updated.
Subscribe
OR

Subscribe by RSS

Add our RSS to your feedreader to get regular updates from us.
Subscribe