Abstract :
This systematic review evaluates the effect of architectural detailing and supervisory control on the quantitative
delivery of mega projects in the city of Abuja, Nigeria. Despite their relevance to national development, mega projects in
Abuja continue to be marred by massive cost overruns and long delays, with average cost overruns of 44.46%, and 68% of
capital projects with delays for more than two years. While dominant discourse points to macro-level issues such as funding
and corruption as a major contributor to these failures, the role of micro-technical processes is under synthesized. This
review addresses this lack of evidence by aggregating and appraising evidence published in peer reviewed journals,
institutional reports, case studies, and media investigations published between 2000 and 2025. Grounded in the theoretical
integration of Project Success Theory and the Rework Cycle Model, the study used thematic and content analysis within an
interpretivist approach. Findings show that architectural detailing shortcomings (as evidenced by incomplete documentation,
coordination failures, and ambiguous specifications) result in cycles of rework that cost 10-20% of project costs. Weak
supervisory control and lack of clear authority and communication allow these cycles to be enhanced with investigations of
building collapse reporting 300+ deaths in Abuja due to supervision failures. The National Library Headquarters project is
an example of such failure with a cost escalation of 2,300% over 18 years. The research proposes a conceptual framework
of how comprehensive detailing and empowered supervision relate to quantitative success mediated by project governance
and institutional capacity. This review concludes that the attention of micro technical processes is critical in improving mega
project in Abuja in the challenging environment.
Keywords :
Architectural Detailing, Construction Supervision, Mega Projects, Cost Overruns, Project Failure, Abuja, Nigeria, Rework Cycle Model.
References :
- Abass, I. (2023). The complexities of construction project management in developing countries: A case study of Nigeria [Master’s dissertation, Salford University]. Scribd. https://www.scribd.com/document/672046028/Abass-s-Dissertation
- Abdulkadir, S., Muhammad, A. I., Gidado, U. M., & Nuruddeen, U. (2017). Cost and time overrun in building projects: Professional attitude and incidence rate in practice. International Journal of Economics, Commerce and Management, 5(8), 276–292. http://ijecm.co.uk/wp-content/uploads/2017/08/5814.pdf
- Abubakar, M. (2023). Causes and effects of rework in Nigerian construction industry. Journal of the Nigerian Institute of Building, 18(2), 45–59.
- Adama, O. (2018). Urban imaginaries: funding mega infrastructure projects in Lagos, Nigeria. GeoJournal, 83(2), 257-274.
- African Development Bank. (2022). Nigeria Country Strategy Paper 2020–2024: Mid-Term Review and 2022 Country Portfolio Performance Review. Abidjan: AfDB. https://www.afdb.org/en/documents/nigeria-country-strategy-paper-2020-2024-mid-term-review-mtr-and-2022-country-portfolio-performance-review-cppr-report
- Agusto & Co. (2024). 2024 infrastructure industry report. https://www.agustoresearch.com/report/2024-infrastructure-industry-report/
- Ahmed, S., & El-Sayegh, S. (2021). Critical review of the evolution of project delivery methods in the construction industry. Buildings, 11(1), 11. https://doi.org/10.3390/buildings11010011
- Aibinu, A. A., & Jagboro, G. O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, 20(8), 593–599. https://doi.org/10.1016/S0263-7863(02)00028-5
- Akinsiku, O. E., & Babalola, O. (2018). Evaluation of factors influencing cost overruns in construction projects in South-West Nigeria. Journal of Construction Project Management and Innovation, 8(1), 1804–1817.
- Asiedu, R. O., & Adaku, E. (2020). Cost overruns of public sector construction projects: A developing country perspective. International Journal of Managing Projects in Business, 13(1), 66–84. https://doi.org/10.1108/IJMPB-09-2018-0177
- Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337–342. https://doi.org/10.1016/S0263-7863(98)00069-6
- Banihashemi, S., Assadimoghadam, A., Hajirasouli, A., LeNguyen, K., & Mohandes, S. R. (2025). Parametric design in construction: A new paradigm for quality management and defect reduction. International Journal of Construction Management, 25(13), 1534–1551.
- Baranda-Rodriguez, E., González, R. G., & Rosas Mayoral, J. G. (2025). Review of the role of building information modelling-based constructability in improving sustainability in industrial plant construction projects. Buildings, 15(11), 1921. https://doi.org/10.3390/buildings15111921
- Bello, S. M. (2025). Promises and Realities of Smart City Projects in Africa: The Abuja Centenary Economic City (ACEC) in Nigeria [Master’s thesis, Ohio University]. https://etd.ohiolink.edu/acprod/odb_etd/ws/send_file/send?accession=ohiou1755184149610511&disposition=inline
- Bizley, G. (2025). Architecture in detail. https://prewettbizley.com/architecture-in-detail/
- Budget Office of the Federation. (2023). 2022 Fourth Quarter and Full Year Budget Implementation Report. Abuja: Federal Government of Nigeria. https://budgetoffice.gov.ng/index.php/resources/internal-resources/reports/quarterly-budget-implementation/2022-budget-implementation-report/2022-fourth-quarter-budget-implementation-report-2
- Ching, F. D. K., & Adams, C. (2014). Building construction illustrated (5th ed.). John Wiley & Sons.
- CIOB. (2014). The Clerk of Works: A guide to the role. Chartered Institute of Building.
- Cooper, K. G. (1993). The rework cycle: Benchmarks for the project manager. Project Management Journal, 24(1), 17–22.
- Dada, M. O. (2019). Causes and effects of delayed payments on construction projects in Nigeria. Journal of Financial Management of Property and Construction, 24(2), 145–160.
- Dalibi, S. G. (2016). Factors affecting construction supervision effectiveness in Nigerian public projects. Journal of Building Performance, 7(1), 34–47.
- Dimitriou, H. T., Ward, E. J., & Dean, M. (2013). Mega transport projects—Beyond the 'iron triangle': Findings from the OMEGA research programme. Progress in Planning, 86, 1–43. https://doi.org/10.1016/j.progress.2013.04.001
- Drummond, F. (2025). 5 Making Creative Work Work Beyond the City. African Urban Creativity: Exploring Creative Economies Within and Beyond Cities.
- Dutum Group. (2025). The critical role of clerk of works in mega project delivery in Nigeria. Dutum Construction Review, 12(1), 8–15.
- Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2018). BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors (3rd ed.). John Wiley & Sons.
- Egan, J. (1998). Rethinking construction. Department of Trade and Industry.
- Egila, A. E., Balogun, O. A., & Yusuf, S. O. (2020). Assessment of delay and cost-overrun in federal road construction project in Abuja. Independent Journal of Management & Production, 11(4), 1184-1200.http://www.ijmp.jor.br/index.php/ijmp/article/view/1065/1383
- Ekponyoh, U. D., George, W. K., Etuk, E. R., Elijah, E. S., & Kabari, A. D.(2025). Building Collapse in Abuja and Lagos Between 1984 and 2023: Assessing Structural Vulnerabilities to Prevent Reoccurrence. https://www.researchgate.net/publication/398772621_Building_Collapse_in_Abuja_and_Lagos_Between_1984_and_2023_Assessing_Structural_Vulnerabilities_to_Prevent_Reoccurrence
- Ellis, J., Edwards, D. J., Thwala, W. D., Ejohwomu, O., Ameyaw, E. E., & Shelbourn, M. (2021). A case study of a negotiated tender within a small-to-medium construction contractor: Modelling project cost variance. Buildings, 11(6), 260. https://doi.org/10.3390/buildings11060260
- Fageha, M. K., & Aibinu, A. A. (2013). Managing project scope definition to improve stakeholders’ participation and enhance project outcome. Procedia - Social and Behavioral Sciences, 74, 154–164. https://doi.org/10.1016/j.sbspro.2013.03.038
- Ferguson, H. (2013). Buildability: A design philosophy. Construction Industry Research and Information Association.
- Flyvbjerg, B. (2017). The Oxford handbook of megaproject management. Oxford University Press.
- Heinrich Böll Foundation. (2023). Abuja, city for all? Challenges and recommendations for an inclusive capital. Heinrich Böll Stiftung. https://ng.boell.org/en/2023/09/25/abuja-city-all
- Infrastructure Concession Regulatory Commission. (2021). 2021 Annual report. ICRC. https://www.icrc.gov.ng/portfolio-item/2021-annual-report/
- Iroha, E. V., Watanabe, T., & Satoshi, T. (2024). Flawed institutional structures: project managers underutilized in Nigeria’s construction industry. Buildings, 14(3), 807.
- Jimoh, R. A., Oyewobi, L. O., Adamu, A. N., & Bajere, P. A. (2017). Influence of supervision on labour productivity on construction sites in Abuja-Nigeria. Independent Journal of Management & Production, 8(1), 88–109. https://doi.org/10.14807/ijmp.v8i1.523
- Kamara, J. M., Anumba, C. J., & Evbuomwan, N. F. O. (2002). Capturing client requirements in construction. Thomas Telford.
- Latham, M. (1994). Constructing the team. HMSO.
- Liman, D. (2025, September 5). NLA urges FG to complete National Library project. Daily Trust. https://dailytrust.com/nla-urges-fg-to-complete-national-library-project/
- Love, P. E. D., & Edwards, D. J. (2004). Forensic project management: The underlying causes of rework in construction projects. Civil Engineering and Environmental Systems, 21(3), 207–228. https://doi.org/10.1080/10286600412331314144
- Love, P. E. D., & Smith, J. (2016). Toward error management in construction: Moving beyond a zero vision. Journal of Construction Engineering and Management, 142(11), 04016058. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001170
- Love, P. E. D., Holt, G. D., Shen, L. Y., & Irani, Z. (2002). Using systems dynamics to better understand change and rework in construction project management systems. International Journal of Project Management, 20(6), 425–436. https://doi.org/10.1016/S0263-7863(01)00039-4
- Love, P. E. D., Smith, J., Ackermann, F., & Irani, Z. (2019). Making sense of rework and its unintended consequence in projects: The emergence of uncomfortable knowledge. International Journal of Project Management, 37(3), 501–516. https://doi.org/10.1016/j.ijproman.2019.02.004
- Love, P. E. D., Teo, P., & Morrison, J. (2016). Unearthing the nature and interplay of quality and safety in construction projects. Journal of Construction Engineering and Management, 142(8), 04016030. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001125
- Melo, É. (2022, December 1). Do you know Cooper’s “rework cycle”? LinkedIn. https://www.linkedin.com/pulse/do-you-know-coopers-rework-cycle-%C3%A9rika-melo-dba-pmp/
- Moses, T. (2024, August 26). 18 years after: N49.6bn National Library project in a shambles. Leadership. https://leadership.ng/18-years-after-n49-6bn-national-library-project-in-a-shambles/
- Nigeria Real Estate Hub. (2018). Nnamdi Azikiwe International Airport new terminal: The hidden cost of design changes. https://nigerianrealestatehub.com/abuja-airport-terminal-cost/
- Office of the Auditor-General for the Federation. (2021). Annual report on the accounts of the federation of Nigeria. OAuGF.
- Ofori, G. (2015). Nature of the construction industry, its needs and its development: A review of four decades of research. Journal of Construction in Developing Countries, 20(2), 115–135.
- Ogbemudia, C. E., et al. (2021). An investigation into causes of building collapse in Abuja, Nigeria. Global Scientific Journal. https://www.globalscientificjournal.com/researchpaper/AN_INVESTIGATION_INTO_CAUSES_OF_BUILDING_COLLAPSE_IN_ABUJA_NIGERIA.pdf
- Ogunbiyi, O. E. (2014). The impact of poor supervision on building defects in Nigeria. Journal of Environmental Technology, 8(2), 101–115.
- Ogundeji, J., & Ikpoto, E. (2023, August 30). Rising cost: Building firms struggle with abandoned projects, job cuts. The Punch. https://punchng.com/rising-cost-building-firms-struggle-with-abandoned-projects-job-cuts/
- Okhueleigbe, C. (2023). Mitigating Building Collapse in Nigeria Through Effective Project Quality Management Practices.
- Olanrewaju, S. D., & Ogunmakinde, O. E. (2020). Waste minimisation strategies at the design phase: Architects' response. Waste Management, 118, 323-330.
- OLAROTIMI, A. E. (2022). EVALUATION OF CRITICAL SUCCESS FACTORS FOR PUBLIC-PRIVATE PARTNERSHIP’S REMODELLED MARKET PROJECTS IN ABUJA, NIGERIA (Doctoral dissertation).
- Olatunji, O. A., Rotimi, J. O. B., Rotimi, F. E., & Silva, C. W. (2025). Causal relationship between project financing and overruns in major dam projects in Africa. Engineering, Construction and Architectural Management, 32(10), 6480–6508.
- Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509–526. https://doi.org/10.1080/01446191003674519
- Olowolayemo, O. (2023). Factors Responsible for Deficient Supervision of Construction Project in the Nigerian Building Construction Industry.
- Oluyemi-Ayibiowu, B. D., Aiyewalehinmi, O. E., & Omolayo, O. J. (2019). Most critical factors responsible for cost overruns in Nigeria building construction industry. J. Multidiscip. Eng. Sci. Stud, 5, 2500-2508.
- Opawole, A., Jagboro, G. O., & Babalola, O. (2020). Evaluation of the causes and effects of project failure in Nigerian public construction sector. Journal of Construction in Developing Countries, 25(1), 1–21.
- Owolabi, J. D., Amusan, L. M., Oloke, C. O., Olusanya, O., Tunji-Olayeni, P., Owolabi, D., Peter, J., & Omuh, I. (2014). Determinants of construction supervision effectiveness in Nigeria. Mediterranean Journal of Social Sciences, 5(27), 1356–1364.
- Oyenuga, V. O. (2025). Architectural detailing and construction supervision: Lessons from Abuja mega projects. Journal of the Nigerian Institute of Building, 20(1), 5–19.
- Pham, V. B., Wong, S. P. P., & Abbasnejad, B. (2025). A systematic review of criteria influencing the integration of BIM and immersive technology in building projects.
- Premium Times. (2017, November 14). Inside the crisis, controversies of Abuja airport terminal project. https://www.premiumtimesng.com/news/headlines/250970-inside-crisis-controversies-abuja-airport-terminal-project.html
- Radio Nigeria. (2025, January 26). Abuja second runway project faces delays amid cost overruns. https://radionigeria.gov.ng/2025/01/26/abuja-second-runway-project-faces-delays-amid-cost-overruns
- Rahmandad, H., & Hu, K. (2010). Modeling the rework cycle: Capturing multiple defects per task. System Dynamics Review, 26(3), 233–260. https://doi.org/10.1002/sdr.445
- Revizto. (2025). Understanding the architectural design phases and stages of the process. https://revizto.com/resources/blog/architectural-design-phases-stages
- Runsewe, D. (2025, February 6). The African Medical Centre of Excellence (AMCE), Abuja - Federal Capital Territory. Estate Intel. https://estateintel.com/insights/the-african-medical-centre-of-excellence-amce
- Rwelamila, P. D., & Hall, K. A. (1995). Total quality management and the construction industry: A review. Journal of Construction Engineering and Management, 121(2), 177–185. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:2(177)
- Saidu, I., & Shakantu, W. (2017). An investigation into cost overruns for ongoing building projects in Abuja, Nigeria. Acta Structilia, 24(1), 53–72. https://doi.org/10.18820/24150487/as24i1.3
- The Guardian Nigeria. (2024, May 23). 18-year-old construction work: From N9b in 2006, abandoned national library to cost over N200b. https://guardian.ng/news/18-year-old-construction-work-from-n9b-in-2006-abandoned-national-library-to-cost-over-n200b/
- The Guardian Nigeria. (2024, May 8). Senate probes $18.5b Abuja centenary city project. https://guardian.ng/news/senate-probes-18-5b-abuja-centenary-city-project
- The Guardian. (2024, August 3). Why many reforms fail in Nigeria... a foundation's search for answers. The Guardian Nigeria. https://guardian.ng/opinion/why-many-reforms-fail-in-nigeria-a-foundations-search-for-answers/
- Toor, S. U. R., & Ogunlana, S. O. (2010). Beyond the 'iron triangle': Stakeholder perception of key performance indicators (KPIs) for large-scale public sector development projects. International Journal of Project Management, 28(3), 228–236. https://doi.org/10.1016/j.ijproman.2009.05.005
- Yap, J. B. H., Shavarebi, K., & Skitmore, M. (2021). Capturing and reusing knowledge: Analysing the what, how and why for construction planning and control. Production Planning & Control, 32(11), 875–888. https://doi.org/10.1080/09537287.2020.1759832
- Zerihun, A., Beza, D., & Idris, M. J. (2025). Factors affecting contractor and subcontractor relationship and their effects on building project performance: Case of Addis Ababa. International Journal of Construction Management. https://doi.org/10.1080/15623599.2025.1234567
- Żurawiecki, J. (2023, July 12). Navigating the triple constraints in project management. BigPicture. https://bigpicture.one/blog/triple-constraints-in-project-management/
This systematic review evaluates the effect of architectural detailing and supervisory control on the quantitative
delivery of mega projects in the city of Abuja, Nigeria. Despite their relevance to national development, mega projects in
Abuja continue to be marred by massive cost overruns and long delays, with average cost overruns of 44.46%, and 68% of
capital projects with delays for more than two years. While dominant discourse points to macro-level issues such as funding
and corruption as a major contributor to these failures, the role of micro-technical processes is under synthesized. This
review addresses this lack of evidence by aggregating and appraising evidence published in peer reviewed journals,
institutional reports, case studies, and media investigations published between 2000 and 2025. Grounded in the theoretical
integration of Project Success Theory and the Rework Cycle Model, the study used thematic and content analysis within an
interpretivist approach. Findings show that architectural detailing shortcomings (as evidenced by incomplete documentation,
coordination failures, and ambiguous specifications) result in cycles of rework that cost 10-20% of project costs. Weak
supervisory control and lack of clear authority and communication allow these cycles to be enhanced with investigations of
building collapse reporting 300+ deaths in Abuja due to supervision failures. The National Library Headquarters project is
an example of such failure with a cost escalation of 2,300% over 18 years. The research proposes a conceptual framework
of how comprehensive detailing and empowered supervision relate to quantitative success mediated by project governance
and institutional capacity. This review concludes that the attention of micro technical processes is critical in improving mega
project in Abuja in the challenging environment.
Keywords :
Architectural Detailing, Construction Supervision, Mega Projects, Cost Overruns, Project Failure, Abuja, Nigeria, Rework Cycle Model.