Abstract :
Natural disasters such as earthquakes, liquefaction, and flash floods are natural phenomena; the events of
September 28, 2018 and in 2019 in Central Sulawesi Province resulted in increased sedimentation in the Palu River Basin
and caused infrastructure damage in Sigi Regency. These events formed the basis for the Infrastructure Reconstruction
Sector Loan (IRSL) Program as an effort to control sediment (sabodam) in Namo Village and Bolapapu Village. The supply
chain for project implementation is prone to risks that will impact the timeline, cost, and quality of the work. This study
aims to analyze the construction supply chain risk in the Sediment Control Project (Sabodam) in Sigi Regency using the
Monte Carlo Simulation model. Risk identification is carried out based on the supply chain cycle which includes
specifications, procurement, transportation, and fabrication. The research data was obtained from questionnaires filled out
by ten respondents representing the managerial and operational functions of the project. The results showed that there were
five main risks that significantly affected project implementation, namely changes in material prices, material scarcity,
materials without permits (IUP), vendors not registered in the system, and transportation disruptions due to field conditions
such as landslides.
Keywords :
Supply Chain Risk; Monte Carlo Simulation; Construction Project.
References :
- Ahmed, Hani. (2017). Impact Assessment of Construction Supply Chain Risk Changes on Project Time and Cost.University of Waterloo-Canada.
- Almamlook, R., Bzizi, M., Al-Kbisbeh, M., Ali, T., & Almajiri, E. (2020). Factors Affecting Labor Productivity in the Construction Industry. American Journal of Environmental Science and Engineering, 4(2), 24. https://doi.org/10.11648/j.ajese.20200402.13
- Aloini, D., Dulmin, R., Mininno, V., & Ponticelli, S. (2012). Supply chain management: a review of implementation risks in the construction industry. Business Process Management Journal, 18(5), 735-761.
- Almamlook, R., Bzizi, M., Al-Kbisbeh, M., Ali, T., & Almajiri, E. (2020). Factors Affecting Labor Productivity in the Construction Industry. American Journal of Environmental Science and Engineering, 4(2), 24. https://doi.org/10.11648/j.ajese.20200402.13
- Amalia, K., & Info, A. (2023). RISIKO DALAM PENERAPAN RANTAI PASOK MATERIAL PADA PROYEK INFRASTRUKTUR JALAN. 2(2), 153–161.
- Czajkowska, A., & Ingaldi, M. (2025). Supply chain risk management in construction. Advances in Science and Technology Research Journal, 19(8), 15–29. https://doi.org/10.12913/22998624/204013
- Djohim, M. F. N., Nugroho, A. S. B., & Handayani, T. N. (2024). Risk Analysis of Modest Housing Projects Scheduling using Monte Carlo Simulation. Civil Engineering Dimension, 26(2), 160–172. https://doi.org/10.9744/ced.26.2.160-172
- Fassa, F., Wibowo, A., & Soekiman, A. (2021). Sumber Daya Manusia di Industri Konstruksi Periode 2011-2020: Faktor-Faktor yang Mempengaruhi Produktivitas Tenaga Kerja Konstruksi: Sebuah Tinjauan Sistematis. Simposium Nasional Teknologi Infrastruktur Abad Ke-21 , February, 249–254. https://www.researchgate.net/publication/349669895
- Hadi, J. A., Febrianti, M. A., & Yudhistira, G. A. (2020). Identifikasi Risiko Rantai Pasok dengan Metode House of Risk ( HOR ). 19(2), 85–94. https://doi.org/10.20961/performa.19.2.46388
- Harsoyo, Y. A., & Rahman, R. F. (2023). Analisis Risiko Flow Information dalam Construction Supply Chain dengan Tinjauan Pekerjaan Pondasi Rakit. Bulletin of Civil Engineering, 2(2), 91–100. https://doi.org/10.18196/bce.v2i2.12419
- Kurniawan, H., & Anggraeni, I. A. A. (2020). ANALISIS RISIKO RANTAI PASOK MATERIAL TERHADAP KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI. 14(1), 43–50.
- Layaq, M. W., & Goudz, A. (2020). Monte Carlo Simulation Concept for Demand Risk Identification in a Supply Chain. 4863.
- Rani, H. A., Amin, J., Ayob, A., & Al Rahmatillah, D. (2022). Risk Probability of Time and Cost on Building Construction Project: A Monte Carlo Simulation. JIT Journal of Innovation and Technology, 3(2), 2721–8570. https://doi.org/10.31629/jit.v3i2.5192
- Utomo, J., Hatmoko, D., & Kistiani, F. (2017). Model Simulasi Risiko Rantai Pasok Material Proyek Konstruksi Gedung. 23(1), 1–13.
- Ballard, G., and Howell, G. (1998). “What kind of production is construction?”.
- Proc., 6th Ann. Conf. Int. Group for Lean Constr., IGLC, Guaruja, Brazil.
- Chapman, Chris, Et all. (2003). Project Risk Management Second Edition: Processes, techniques, and Insight. School of Management, University of Southampton, UK.
- Construction Industry Institute (2012). Applying Probabilistic Risk Management in Design and Construction Projects. Austin, Texas: Construction Industry Institute.
- Construction Industry Institute (1999). Procurement and Materials Management: A Guide to Effective Project Execution. University of Texas at Austin. Austin: Construction Industry Institute.
- Cox, A., & Ireland, P. (2002). Managing construction supply chain: The common sense approach. Engineering, Construction and Architectural Management, 9(5-6), 409- 418.
- Czajkowska, A., & Ingaldi, M. (2025). Supply chain risk management in construction. Advances in Science and Technology Research Journal, 19(8), 15–29. https://doi.org/10.12913/22998624/204013
- Djohim, M. F. N., Nugroho, A. S. B., & Handayani, T. N. (2024). Risk Analysis of Modest Housing Projects Scheduling using Monte Carlo Simulation. Civil Engineering Dimension, 26(2), 160–172. https://doi.org/10.9744/ced.26.2.160-172
Natural disasters such as earthquakes, liquefaction, and flash floods are natural phenomena; the events of
September 28, 2018 and in 2019 in Central Sulawesi Province resulted in increased sedimentation in the Palu River Basin
and caused infrastructure damage in Sigi Regency. These events formed the basis for the Infrastructure Reconstruction
Sector Loan (IRSL) Program as an effort to control sediment (sabodam) in Namo Village and Bolapapu Village. The supply
chain for project implementation is prone to risks that will impact the timeline, cost, and quality of the work. This study
aims to analyze the construction supply chain risk in the Sediment Control Project (Sabodam) in Sigi Regency using the
Monte Carlo Simulation model. Risk identification is carried out based on the supply chain cycle which includes
specifications, procurement, transportation, and fabrication. The research data was obtained from questionnaires filled out
by ten respondents representing the managerial and operational functions of the project. The results showed that there were
five main risks that significantly affected project implementation, namely changes in material prices, material scarcity,
materials without permits (IUP), vendors not registered in the system, and transportation disruptions due to field conditions
such as landslides.
Keywords :
Supply Chain Risk; Monte Carlo Simulation; Construction Project.