Delayed Ring Closure as the Primary Cause of Tunnel Collapse in Swelling Claystone: A Lesson from Jatigede Hydroelectric Power Project, Indonesia


Authors : Kaustubh Mani Nepal

Volume/Issue : Volume 11 - 2026, Issue 9 - September


Google Scholar : https://tinyurl.com/2ndnerpe

DOI : https://doi.org/10.38124/ijisrt/26sep312

Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.


Abstract : severe squeezing near the collapse zone, with asymptotic convergences up to 1,421 mm and creep ratios as high as 6.5; (b) moderate creep at varying distances; and (c) limited deformation in more competent ground. The lessons learned from this analysis underscore the critical need for immediate ring closure in squeezing ground, the importance of systematic rock bolting, the effectiveness of real-time monitoring, and the value of customized support systems for managing swelling ground conditions. These findings provide essential insights that will significantly improve tunnel construction practices in similar geological contexts.

Keywords : Squeezing Ground; Tunnel Collapse; Convergence Monitoring; Swelling Claystone; Ring Closure; Time-Dependent Deformation.

References :

  1. Sulem, J., Panet, M., and Guenot, A. (1987). Closure analysis in deep tunnels. International Journal of Rock Mechanics and Mining Sciences & Geomechanics Abstracts, 24(3), 145-154.
  2. Bieniawski, Z. T. (1989). Engineering Rock Mass Classifications. Wiley-Inter-Science.
  3. Hoek, E., and Brown, E. T. (1997). Practical estimates of rock mass strength. International Journal of Rock Mechanics and Mining Sciences, 34(8), 1165-1186.
  4. World Stress Map (2016). World Stress Map Database Release 2016. GFZ Potsdam.
  5. Aydan, Ö., Akagi, T., & Kawamoto, T. (1993). The squeezing potential of rocks around tunnels: Theory and prediction. Rock Mechanics and Rock Engineering, 26(2), 137-163.
  6. Singh, B., and Goel, R. K. (2006). Tunnelling in Weak Rocks. Elsevier Geo-Engineering Book Series, Volume 5.
  7. Barla, G. (1995). Squeezing rocks in tunnels. ISRM News Journal, 2(3/4), 44-49.
  8. Manuel de la Fuente Mata. (2018). Tunnelling under squeezing conditions: Effect of the excavation method. École Doctorale Sciences, Ingénierie et Environnement (SIE), Thèse de doctorat.
  9. Thakur, P. K. (2005). Analysis of Time-Dependent Response of Tunnels Considering Creep Effect. Asian Institute of Technology, School of Civil Engineering, Master of Engineering, Thesis.
  10. Frenelus, W., and Peng, H. (2023). Evaluating the Time-Dependent Behaviour of Deeply Buried Tunnels in Soft Rock Environments and Relevant Measures Guaranteeing Their Long-Term Stability. Applied Sciences, 13(18), 10542. https://doi.org/10.3390/app131810542.
  11. Barlow, J. P. (1986). Interpretation of Tunnel Convergence Measurements. Master Thesis, The University of Alberta, Department of Civil Engineering.
  12. Huang, J., Liu, X. W., et al. (2023). The stability evaluation of clay tunnels via the non-linear deterioration of physical and mechanical properties of surrounding rocks. Frontiers in Geoscience.
  13. Panthi, K. K. (2013). Predicting Tunnel Squeezing: A Discussion based on Two Tunnel Projects. Hydro Nepal, Issue 12, January 2013.
  14. Lee, C.H., Wang, T.T., Sun, L.J., and Huang, T.H. (2013). Invert heaving in operational tunnels – problems and countermeasures. In Proceedings of the World Tunnel Congress 2013 Geneva – Underground: The Way to the Future! (pp. 770–777). Taylor & Francis Group, London.
  15. Bonini, M., et al. (2009). The Mechanical Behaviour of Clay Shales and Implications for the Design of Tunnels. Rock Mechanics and Rock Engineering, 42, 361–388. DOI 10.1007/s00603-007-0147-6.
  16. Project Internal Report (2020). Submission of Completion Report on Water Inrush, Collapse, Mud Burst Penstock Tunnel PS0+290.
  17. Project Internal Report (2022a). Contractor Clarification on Tunnel Claims.
  18. Project Internal Report (2022b). Detailed Design Calculation and Analysis for the Surrounding Rock Stability of Penstock Tunnel from PS0+240m to PS0+390m (Rev. A).
  19. Steiner, W. (2000). Squeezing rock in Tunnelling: Identification and Important Factors. Rivista Italiana Di Geotecnica, 1/2000.
  20. Project Internal Report (2022c). Treatment of Serious Deformation at Penstock Tunnel.
  21. Gall, V., and Pyakurel, S., et al. (2017). Conventional Tunnelling in Difficult Ground. Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
  22. Jatigede Hydroelectric Power Plant, Tender Design Report. Xibei Engineering Corporation, China. September 2013.
  23. Jatigede Multi-Purpose Dam Project, Criteria and Basic Design Report Vol 1. (1986). Snowy Mountains Engineering Corporation (SMEC), Australia in Association with Indra Karya, Cirebon, Indonesia.
  24. Shimamoto, K., Yashiro, K., and Kawagoe, T. (2022). Floor heave and Effect of countermeasure for Mountain Tunnels. Quarterly Reports of Railway Technical Research Institute, RTRI Vol. 63-2, pp. 115-120.
  25. Saroglou, C. (2025). The Challenge of Rock Mass Classification of Anisotropic Rock Masses. Rock Mechanics and Rock Engineering. https://doi.org/s00603-025-04681-8.
  26. Hoek, E., and Guevara, R. (2009). Overcoming Squeezing in the Yacambú-Quibor Tunnel, Venezuela. Rock Mechanics and Rock Engineering, 42(2), 389-418. DOI:10.1007/s00603-009-0175-5.

severe squeezing near the collapse zone, with asymptotic convergences up to 1,421 mm and creep ratios as high as 6.5; (b) moderate creep at varying distances; and (c) limited deformation in more competent ground. The lessons learned from this analysis underscore the critical need for immediate ring closure in squeezing ground, the importance of systematic rock bolting, the effectiveness of real-time monitoring, and the value of customized support systems for managing swelling ground conditions. These findings provide essential insights that will significantly improve tunnel construction practices in similar geological contexts.

Keywords : Squeezing Ground; Tunnel Collapse; Convergence Monitoring; Swelling Claystone; Ring Closure; Time-Dependent Deformation.

Paper Submission Last Date
30 - September - 2026

SUBMIT YOUR PAPER CALL FOR PAPERS
Video Explanation for Published paper

Never miss an update from Papermashup

Get notified about the latest tutorials and downloads.

Subscribe by Email

Get alerts directly into your inbox after each post and stay updated.
Subscribe
OR

Subscribe by RSS

Add our RSS to your feedreader to get regular updates from us.
Subscribe