Authors :
Pradita Utari; Neny Fidayanti; Ferdinandus; Yossa Yonathan Hutajulu; Dody Ariyantho Kusma Wijaya
Volume/Issue :
Volume 10 - 2025, Issue 6 - June
Google Scholar :
https://tinyurl.com/bdf6uuv3
DOI :
https://doi.org/10.38124/ijisrt/25jun1618
Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.
Abstract :
CV Bintari Jaya Abadi is a company engaged in andesite stone mining. The actual productivity of the excavator
at the CV Bintari Jaya Abadi quarry in January 2024 was recorded at 9,494.8111 BCM, while the hauling equipment
achieved 9,362.83824 BCM, with a match factor of 0.68. This resulted in the current andesite mining target not being
achieved, where the targeted andesite rock removal at CV Bintari Jaya Abadi is 11,538 BCM per month. The research
method used involved the calculation and quantitative analysis of the factors affecting the match factor between loading
and hauling equipment in andesite mining activities at CV Bintari Jaya Abadi. Improvement efforts aimed at achieving
optimal productivity and operational compatibility were carried out by optimizing the cycle times of both the loading and
hauling equipment. As a result, the productivity of the loading equipment increased by 34.71% to 12,790.0415
BCM/month, and the productivity of the hauling equipment increased by 76.34% to 16,509.7606 BCM/month, successfully
meeting and even exceeding the target set by CV Bintari Jaya Abadi of 11,538 BCM/month, with a match factor of 0.94.
Keywords :
Cycle Time; Delay Time; Match Factor; Production; Work Efficiency
References :
- G. Adilah, M. A., Tono, E. P. S. B. T., & Andini, D. E. (2019). Evaluation of Work Compatibility Between Excavation and Hauling Equipment to Achieve a Limestone Production Target of 350,000 Tons/Month at Pit 242 Bukit Karang Putih PT Semen Padang (Persero) in Lubuk Kilangan District, West Sumatra [Undergraduate thesis, Bangka Belitung University].
- Aksyal, A. A. (2021). Technical Study on the Production of Loading and Hauling Equipment to Meet Nickel Ore Production at PT Makmur Lestari Primatama, Langgikima District, North Konawe Regency, Southeast Sulawesi [Undergraduate thesis, Universitas Pembangunan Nasional Veteran Yogyakarta].
- Andi, S. (2019). Optimization of Loading and Hauling Equipment Production for Coal Removal in Coal Handling Operations 4, Penbara East Block, PT Bukit Asam Tbk, Muara Enim Regency, South Sumatra [Undergraduate thesis, Universitas Pembangunan Nasional Veteran Yogyakarta].
- Anggara, D., Franto, & Guskarnali. (2024). Evaluation of the match factor of excavation and hauling equipment to improve overburden stripping productivity at PT Cipta Kridatama. Jurnal Himasapta, 9(1), 13–20. https://doi.org/10.20527/jhs.v9i1.9373
- Basuki, W., Oktavia, M., & Elfistoni, A. (2020). Calculation of Dump Truck Requirements Based on Match Factor and Queuing Theory in Coal Mining at PT Kamalindo Sompurna, Pelawan District, Sarolangun Regency, Jambi Province. Mine Magazine, 1(2). https://doi.org/10.36355/.v1i2.398
- Budiwaskito, R. (2010). Margin of Error. Bandung Institute of Technology.
- Fandini, M. I., & Yulhendra, D. (2022). Evaluation of the Work Compatibility Between Komatsu PC300-8LC Excavator and Scania P360 Dump Truck at the PNBP VI Area to Support the Achievement of Limestone Production Target in August 2022 at PT Semen Padang. Jurnal Bina Tambang, 7(3), 158–168. https://doi.org/10.24036/bt.v7i3.120582
- Febriani, S. (2022). Descriptive Analysis of Standard Deviation. Jurnal Pendidikan Tambusai, 6(1), 910–913. https://doi.org/10.31004/jptam.v6i1.8194
- Frasetia, M. D., & Saldy, T. G. (2023). Increasing Hauling Equipment Production Capacity to Achieve a Target of 5,000 Tons/Month in Clay Excavation Using the Queuing Method at IUP OP Jumaidi Mine, Gunuang Sariak, West Sumatra. Jurnal Bina Tambang, 8(1), 136–144. https://doi.org/10.24036/bt.v8i1.122194
- Insani, R. W. S. (2020). Understanding Confidence Intervals and How to Calculate Them. https://www.rachmatwahid.com/2020/05/selang-kepercayaan-hitung.html
- Jenius, Bargawa, W. S., & Gingga, F. (2019). Investment and Equipment Leasing Evaluation for Overburden Stripping and Nickel Ore Excavation in GC Padakmpra Hill, Gee Island, Maba District, East Halmahera Regency. Proceedings of the 7th National Seminar on Applied Science and Technology, Institut Teknologi Adhi Tama Surabaya, 557–562.
- Kusnama. (2008). Warukin Formation Coal in Sampit Area and Surroundings, Central Kalimantan. Indonesian Journal of Geology, 3(1), 11–22.
- Munandar, M. A., & Halim, A. (2020). Confidence Interval for Proportions. Community Ophthalmology Unit, Cicendo Eye Hospital, Universitas Padjadjaran Bandung.
- Peurifoy, R. L., Schexnayder, C., Shapira, A., & Schmitt, R. L. (2011). Construction Planning, Equipment and Methods (8th ed.). McGraw-Hill.
- Rahman, F. (2021). Technical Study on the Work Compatibility of Loading and Hauling Equipment in Andesite Production at PT Eka Praya Jaya, East Lombok Regency [Diploma thesis, University of Muhammadiyah Mataram].
- Saputra, F. (2018). Productivity Study of Digger and Hauler on Overburden Stripping at Pit S5 South. Indonesian Mining and Energy Journal, 1(1), 29–39.
- Tenriajeng, A. T. (2003). Earthmoving Operations. Jakarta: Gunadarma.
- Wahyudi, F., Tibri, T., & Sedarta. (2022). Evaluation of the Productivity of Loading and Hauling Equipment in Coal Mining at PIT Air Laya (TAL) West, PT Bukit Asam Tbk, Tanjung Enim, South Sumatra. Journal of Interior and Exterior Space FTSP, 4(2), 226–231.
- Wigroho, H. Y., & Suryadharma, H. (1993). Earthmoving Operations. Atma Jaya University Yogyakarta.
CV Bintari Jaya Abadi is a company engaged in andesite stone mining. The actual productivity of the excavator
at the CV Bintari Jaya Abadi quarry in January 2024 was recorded at 9,494.8111 BCM, while the hauling equipment
achieved 9,362.83824 BCM, with a match factor of 0.68. This resulted in the current andesite mining target not being
achieved, where the targeted andesite rock removal at CV Bintari Jaya Abadi is 11,538 BCM per month. The research
method used involved the calculation and quantitative analysis of the factors affecting the match factor between loading
and hauling equipment in andesite mining activities at CV Bintari Jaya Abadi. Improvement efforts aimed at achieving
optimal productivity and operational compatibility were carried out by optimizing the cycle times of both the loading and
hauling equipment. As a result, the productivity of the loading equipment increased by 34.71% to 12,790.0415
BCM/month, and the productivity of the hauling equipment increased by 76.34% to 16,509.7606 BCM/month, successfully
meeting and even exceeding the target set by CV Bintari Jaya Abadi of 11,538 BCM/month, with a match factor of 0.94.
Keywords :
Cycle Time; Delay Time; Match Factor; Production; Work Efficiency