The Delay Analysis of State Building Construction Projects in South Kalimantan Province


Authors : M. Ridho Ramadhan; Irfan Prasetia

Volume/Issue : Volume 11 - 2026, Issue 1 - January


Google Scholar : https://tinyurl.com/25cv7msc

Scribd : https://tinyurl.com/yeyv8jsz

DOI : https://doi.org/10.38124/ijisrt/26jan630

Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.


Abstract : The success of a project is influenced by performance of each component executive jobs include project owner. Based on nature and objectives, each involve component has different interests, which if not managed optimally would be a potential for the occurrence of disputes in various forms and complexities that can potentially towards increased construction costs and delay completion of the work. Projects are experiencing delays that often recurs in the aspect that influenced and influencing factors. The purpose of this study is to identify the factors that cause delays construction project building government of South Kalimantan Provincial. This research was conducted to find out what factor construction works late and what factors have the most influence works late on construction project building government which financed by SBSN budged in South Kalimantan Provincial. The research method used in this research is a survey research method with a questionnaire media. Data taken previous research and from reconnaissance survey direct speech with expert persons. While the analysis method uses the Relative Importance Index (RII) method. This analysis that study about factor have the most dominant from 50 (fifty) indicators causes works late. From this analysis we know that there are 34 (thirty-four) factors cause construction building of government lates, there are 8 (eight) factors that most influence on construction building of government lates, and there are 8 (eight) mitigation strategies has validation with experts/professional. The strategy most emphasized by experts is the need to use BIM (building information modeling) technology, to conduct regular socialization, and to provide technical guidance or similar events that discuss mitigation strategies in contract control and project management.

Keywords : Procurement of Goods and Services; Construction; Relative Importance Index; Construction Works Late.

References :

  1. Agus Wibowo Wisudanto. (2013). Factors Causing Delays in Building Construction Projects in Kediri.
  2. Andi et al. (2003). Potential Factors That Can Affect Construction Implementation Time.
  3. Ervianto, W. (2004). Control Cycle in Construction Projects.
  4. Haekal Hassan Jante B. Mangare, Pingkan A.K.Pratatis. (2016). Factors Causing Delays in Construction Projects and Alternative Solutions (Case Study: At Manado Town Square III)
  5. Kariem and Dickmann. (1987). Causes of Delays in Project Implementation Time.
  6. Putri, S., & Yuliana, C. (2025). Risk Analysis on the Construction Project of the Governor's Official Residence in South Kalimantan. Journal of Sustainable Technology, 14(01), 44–54.
  7. Republic of Indonesia. (2018). Regulation of the National Public Procurement Agency of the Republic of Indonesia Number 9 of 2018 concerning Guidelines for the Implementation of Procurement of Goods/Services through Providers. Jakarta.
  8. Republic of Indonesia. (2020). Regulation of the Minister of Public Works and Public Housing of the Republic of Indonesia Number 14 of 2020 concerning Standards and Guidelines for Procurement of Construction Services through Providers. Jakarta.
  9. Republic of Indonesia. (2021). Presidential Regulation of the Republic of Indonesia Number 12 of 2021 Amendment to Presidential Regulation Number 16 of 2018 concerning Procurement of Government Goods/Services. Jakarta.
  10. Republic of Indonesia. (2021). Regulation of the National Public Procurement Agency of the Republic of Indonesia Number 12 of 2021 concerning Guidelines for the Implementation of Procurement of Goods/Services through Providers. Jakarta.
  11. Republic of Indonesia. (2025). Presidential Regulation of the Republic of Indonesia Number 46 of 2025 Amendment to Presidential Regulation Number 12 of 2021 concerning Procurement of Government Goods/Services. Jakarta.
  12. Siregar, S. (2013). Quantitative Research Methods. Jakarta: Kencana.
  13. Sugiyono. (2017). Quantitative Research Methods. Bandung: Alfabeta Publisher.

14. Zaneldin. (2005). Causes of Construction Delays in Building Projects in the United Arab Emirates.

The success of a project is influenced by performance of each component executive jobs include project owner. Based on nature and objectives, each involve component has different interests, which if not managed optimally would be a potential for the occurrence of disputes in various forms and complexities that can potentially towards increased construction costs and delay completion of the work. Projects are experiencing delays that often recurs in the aspect that influenced and influencing factors. The purpose of this study is to identify the factors that cause delays construction project building government of South Kalimantan Provincial. This research was conducted to find out what factor construction works late and what factors have the most influence works late on construction project building government which financed by SBSN budged in South Kalimantan Provincial. The research method used in this research is a survey research method with a questionnaire media. Data taken previous research and from reconnaissance survey direct speech with expert persons. While the analysis method uses the Relative Importance Index (RII) method. This analysis that study about factor have the most dominant from 50 (fifty) indicators causes works late. From this analysis we know that there are 34 (thirty-four) factors cause construction building of government lates, there are 8 (eight) factors that most influence on construction building of government lates, and there are 8 (eight) mitigation strategies has validation with experts/professional. The strategy most emphasized by experts is the need to use BIM (building information modeling) technology, to conduct regular socialization, and to provide technical guidance or similar events that discuss mitigation strategies in contract control and project management.

Keywords : Procurement of Goods and Services; Construction; Relative Importance Index; Construction Works Late.

Never miss an update from Papermashup

Get notified about the latest tutorials and downloads.

Subscribe by Email

Get alerts directly into your inbox after each post and stay updated.
Subscribe
OR

Subscribe by RSS

Add our RSS to your feedreader to get regular updates from us.
Subscribe