Analysis of Cost Control and Project Time in Performance Process with Earned Value Method, Case Study: Improvement of Maliku-Bantanan Road in Pulang Pisau District, Indonesia


Authors : Trisanto; Henry Wardhan

Volume/Issue : Volume 6 - 2021, Issue 1 - January


Google Scholar : http://bitly.ws/9nMw

Scribd : https://bit.ly/39xdDR0


Abstract : A construction project is an activity that requires a detailed calculation in its planning. It is not only planning that needs attention, but construction projects have their complexities in terms of management. The management of a construction project has targets that must be fulfilled by a contractor in terms of quality, implementation time, and cost. This study aimed at determining how the application of Earned Value in estimating the cost and project time. This study took a case study on the 8.505 m Maliku-Bantanan road improvement project located in Maliku and Sebangau Kuala sub-district, Pulang Pisau district, Central Kalimantan province, Indonesia. This earned value included budget and cost plans, unit price analysis, and project progress reports processed to obtain BCWS (Budgeted Cost of Work Scheduled), ACWP (Actual Cost of Work Performance), and BCWP (Budgeted Cost of Work Performance)which affected the control of the implementation time and project costs. The results showed that in the fifth month, the BCWP value was IDR 13,668,602,892.99 and the BCWS value was IDR 13,513,565,248.85from the second calculation. The value of BCWS was smaller than the value of BCWP, which was 1.13% of the budget plan. The conditions indicated that the implementation of activities in the field has been following the planned schedule at a lower cost. These results are expected to be used as a guide for contractors and consultants in project planning that are more effective and efficient as well as on quality, time, and cost.

Keywords : Earned Value (EV), Construction Project, BCWS, BCWP

A construction project is an activity that requires a detailed calculation in its planning. It is not only planning that needs attention, but construction projects have their complexities in terms of management. The management of a construction project has targets that must be fulfilled by a contractor in terms of quality, implementation time, and cost. This study aimed at determining how the application of Earned Value in estimating the cost and project time. This study took a case study on the 8.505 m Maliku-Bantanan road improvement project located in Maliku and Sebangau Kuala sub-district, Pulang Pisau district, Central Kalimantan province, Indonesia. This earned value included budget and cost plans, unit price analysis, and project progress reports processed to obtain BCWS (Budgeted Cost of Work Scheduled), ACWP (Actual Cost of Work Performance), and BCWP (Budgeted Cost of Work Performance)which affected the control of the implementation time and project costs. The results showed that in the fifth month, the BCWP value was IDR 13,668,602,892.99 and the BCWS value was IDR 13,513,565,248.85from the second calculation. The value of BCWS was smaller than the value of BCWP, which was 1.13% of the budget plan. The conditions indicated that the implementation of activities in the field has been following the planned schedule at a lower cost. These results are expected to be used as a guide for contractors and consultants in project planning that are more effective and efficient as well as on quality, time, and cost.

Keywords : Earned Value (EV), Construction Project, BCWS, BCWP

Paper Submission Last Date
30 - November - 2026

SUBMIT YOUR PAPER CALL FOR PAPERS
Video Explanation for Published paper

Never miss an update from Papermashup

Get notified about the latest tutorials and downloads.

Subscribe by Email

Get alerts directly into your inbox after each post and stay updated.
Subscribe
OR

Subscribe by RSS

Add our RSS to your feedreader to get regular updates from us.
Subscribe